[2022] NACE-CIP2-001 by CIP Level 2 Actual Free Exam Practice Test [Q47-Q61]

Rate this post

[2022]  NACE-CIP2-001 by CIP Level 2 Actual Free Exam Practice Test

Free CIP Level 2 NACE-CIP2-001 Exam Question

NEW QUESTION 47
Steel shot grit contaminated with oil or grease used in a cetrifugal blast cleaning should be

 
 
 
 

NEW QUESTION 48
External coatings applied to buried pipelines are generally tested for:

 
 
 
 

NEW QUESTION 49
Ideally, documentation requirements should be defined:

 
 
 
 

NEW QUESTION 50
You should bulk store coatings containing isocyanates

 
 
 
 

NEW QUESTION 51
The Inspectors’ goal at the Pre-Job Conference is to:

 
 
 
 

NEW QUESTION 52
The main reason dehumidification is used during coating operations is to

 
 
 
 

NEW QUESTION 53
In which type of concrete are laitance commonly encountered?

 
 
 
 

NEW QUESTION 54
Non-Conformance Reports are designed to:

 
 
 
 

NEW QUESTION 55
When performing inspection in accordance with ASTM D 4138 the Inspector will use:

 
 
 
 

NEW QUESTION 56
The best choice of instrument for holiday testing of thick film concrete coatings is:

 
 
 
 

NEW QUESTION 57
You are the NACE Level 2 Inspector on a project where overcoating of galvanized steel is being performed. The specification references SSPC SP 16 as the surface preparation method. At the pre-job meeting operations personnel make it clear that abrasive blasting will not permitted. The Owner’s representative asks you what other methods might be used.
Of the options shown below, what would be the preferred option in this situation?

 
 
 
 

NEW QUESTION 58
Eddy current DFT gauges are used to measure Dry Film Thickness in which of the following situations:

 
 
 
 

NEW QUESTION 59
You are the NACE Level 2 inspector reviewing the documentation from a NACE Level 1 you notice significant documentation errors.
Your FIRST preferred course of action is to:

 
 
 
 

NEW QUESTION 60
You are working as the only in-house NACE Level 2 Inspector in a shop setting when an independent 3 rd party NACE Level 3 Inspector, representing the owner, presents you with a copy of a Non Conformance Report (NCR) he has written for a NACE2/SSPC SP 10 centrifugal blast which you had previously approved.
Your FIRST preferred course of action is to:

 
 
 
 

NEW QUESTION 61
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector.
Your FIRST preferred course of action is to:

 
 
 
 

NACE NACE-CIP2-001 Actual Questions and Braindumps: https://www.passtestking.com/NACE/NACE-CIP2-001-practice-exam-dumps.html