The PMI-ACP certification test contains 120 questions, which must be completed within 180 minutes. However, out of these 120 items, 20 are pretest questions that will not affect your overall score. They are only included in the exam as a validity testing tool for the actual questions. The certification exam is available in 6 languages, including English, Japanese, Arabic, Portuguese, Korean, and Spanish. It is delivered through the approved Pearson VUE testing centers worldwide. You can check the location of the nearest available center on the Pearson VUE website. You can also sit for your PMI-ACP exam online from the comfort of your home or office supervised by a proctor through Pearson VUE. The test costs $435 for the PMI members and $495 for the non-members.

 

NEW QUESTION 110
A “Scrum of Scrums” meeting is:

 
 
 
 

NEW QUESTION 111
At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient.
What should the project team have done prior to product release?

 
 
 
 

NEW QUESTION 112
What of the following is not a step in the Value Stream Mapping process?

 
 
 
 
 

NEW QUESTION 113
The team estimation game method mainly consists of a:

 
 
 
 

NEW QUESTION 114
Based on the following figure, during Iteration 5, there was an increase in story point value (shown on the graph); however, the team completed all of the work it promised to deliver in the iteration and existing estimates were not changed. From this information, one can inferthat:

 
 
 
 

NEW QUESTION 115
Extreme Programming (XP) defines four basic activities that are performed during the software development process. These include designing, coding, testing and …?

 
 
 
 

NEW QUESTION 116
According to the fundamental principles of Lean Management, errors result from:

 
 
 
 

NEW QUESTION 117
What is one of the main benefits that Lean portfolio management provides to a business?

 
 
 
 

NEW QUESTION 118
Who tracks work remaining in the Product Backlog?

 
 
 
 

NEW QUESTION 119
After completing the release plan, the team realizes that the project is very likely to have a negative ROI. What should the team do?

 
 
 
 

NEW QUESTION 120
Acceptance tests of user stories are specified by the:

 
 
 
 

NEW QUESTION 121
Personas are used in Agile requirements to depict which type of user?

 
 
 
 

NEW QUESTION 122
Prioritize from high to low the sequence of User Story development.

 
 
 
 

NEW QUESTION 123
During iteration planning, the team is discussing the design for a user story.
A team member states that a design document should be started since the system is complex in nature.
Another team member responds that in Agile there is no documentation.
How should the ScrumMaster respond?

 
 
 
 

NEW QUESTION 124
During a daily stand up, the tester engages the developer in a discussion about what will be tested during unit testing versus regression testing. What should the scrum master do?

 
 
 
 

NEW QUESTION 125

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

 
 
 
 

NEW QUESTION 126
Select the statements that are TRUE about the Product Owner. (Choose two.)

 
 
 
 

NEW QUESTION 127
What type of process control is Scrum?

 
 
 
 

NEW QUESTION 128
A team’s technical lead believes that manual testing should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.
What should the scrum master do?

 
 
 
 

NEW QUESTION 129
At the second level of conflict, i.e. Disagreement, Team members distance themselves from one another to ensure they come out OK in the end or to establish a position for compromise they assume will come. They may talk offline with other team members to test strategies or seek advice and support. What becomes as important as solving the problem?

 
 
 
 

NEW QUESTION 130
What are the primary outputs of a release planning session?

 
 
 
 

NEW QUESTION 131
A development team has finished identifying the tasks they will be accountable for during the next sprint. Which of the following tools best provides transparency into the progress throughout the sprint?

 
 
 
 

NEW QUESTION 132
In the Agile Team Stages of Shu Ha Ri, what does ‘Ha’ stand for?

 
 
 
 

NEW QUESTION 133
An organization adopts Agile practices and implements an incremental delivery strategy. If implemented correctly, the company should recognize improved:

 
 
 
 

NEW QUESTION 134
The process of reviewing, testing, and accepting implemented features is called:

 
 
 
 

PMI-ACP Exam Questions Get Updated [2022] with Correct Answers: https://www.passtestking.com/PMI/PMI-ACP-practice-exam-dumps.html